Power Sector


Power Sector

Sector: Power Sub-Sector:  
      i) Electricity
      ii) PDO

Electricity Department

Electrification: Brief Background & Status:

  • Electricity department is responsible & functioning for electrification in AJK.
  • Electricity facility was available to few towns (13,500 Service connections) of District Muzaffarabad & Mirpur up to 1973-74.
  • Since then a continuous program was planned to provide electricity to rural and urban population and upto June 2016 4.267 million population has been served.

 

Electrification: Brief Statistics:

Following electricity distribution network has been expanded to almost 93% population of AJK up to June 2016.

Item

Nos.

Targets

Consumers

618,282

100,000

No. of Villages (electrified)

1,764 (out of 1771)

101

Grid Station  (132 KV)

                       (33 KV)

20

04

08

H.T Lines

11,368.57 KM

980 KM

L.T Lines

19,535 KM

1760 KM

Distribution Transformers

14,836

1700

Losses (Technical + Administrative)

39.7% (20%+19.7%)

10%

Consumption Per Capita

403 KWH

500 KWH

 

Power Development Organization (PDO)

Hydel Power Generation:

Brief, Background & Status

  • PDO was established through an act of legislative assembly in 2014 and is functioning for Generation and Execution of Hydro Power Projects in AJ&K.
  • Private Power Cell (PPC) is also located in PDO & functioning as PDO Node for the provision of one window services to private sector investors.
  • AJ&K due to its topography has abundant Hydro Power resources and identified Hydro Power potential of AJ&K is approximately 9258.620 MW.
  • Entire demand of AJ&K is about 400 MW (at present AJK is getting around 300 MW to 330 MW).
  • Current Power Generation in AJ&K is 2362.820 MW (Including 1100 MW from  Mangla Dam Raising Project and 969 MW Neelum Jhelum Hydro-Electric Project).

 

Hydro Power Potential in AJ&K

 

Sr.#

Status

Nos.

Capacity

1

 

Commissioned

22

2362.820

  1. PDO

16

59.32

       b. WAPDA

2

2069.00

       c.PPC/PPIB

4

234.5

2

Ongoing

14

974.880

  1. PDO (ADP:10 PSDP:1)

11

145.80

       b.PPC/PPIB

3

829.08

3

Upcoming Projects

59

5920.92

  1. Public Sector

(24 Feasibility completed Cap: 130.28 MW + 06 PC-I Cap: 77.45 MW)

30

207.73

      b.Project under process in private sector

(09 PPIB Cap: 3976.7 MW + 18 AJKPPC Cap: 227.49 MW)

27

4204.190

     c.Raw Sites

(Dudhnial: 960 MW, Neelum III & IV 549 MW)

02

1509.00

 

Total (identified)

95

9258.620

 

Total Estimated Requirements of AJ&K = 400 MW   Maximum Power Supply = 330MW

To see/download a Complete picture of Power sector development activities in AJK click on the link below

Complete Picture of Power Development Activities