Power Sector
Power Sector
Sector: | Power | Sub-Sector: | |
i) Electricity | |||
ii) PDO |
Electricity Department
Electrification: Brief Background & Status:
- Electricity department is responsible & functioning for electrification in AJK.
- Electricity facility was available to few towns (13,500 Service connections) of District Muzaffarabad & Mirpur up to 1973-74.
- Since then a continuous program was planned to provide electricity to rural and urban population and upto June 2016 4.267 million population has been served.
Electrification: Brief Statistics:
Following electricity distribution network has been expanded to almost 93% population of AJK up to June 2016.
Item |
Nos. |
Targets |
Consumers |
618,282 |
100,000 |
No. of Villages (electrified) |
1,764 (out of 1771) |
101 |
Grid Station (132 KV) (33 KV) |
20 04 |
08 |
H.T Lines |
11,368.57 KM |
980 KM |
L.T Lines |
19,535 KM |
1760 KM |
Distribution Transformers |
14,836 |
1700 |
Losses (Technical + Administrative) |
39.7% (20%+19.7%) |
10% |
Consumption Per Capita |
403 KWH |
500 KWH |
Power Development Organization (PDO)
Hydel Power Generation:
Brief, Background & Status
- PDO was established through an act of legislative assembly in 2014 and is functioning for Generation and Execution of Hydro Power Projects in AJ&K.
- Private Power Cell (PPC) is also located in PDO & functioning as PDO Node for the provision of one window services to private sector investors.
- AJ&K due to its topography has abundant Hydro Power resources and identified Hydro Power potential of AJ&K is approximately 9258.620 MW.
- Entire demand of AJ&K is about 400 MW (at present AJK is getting around 300 MW to 330 MW).
- Current Power Generation in AJ&K is 2362.820 MW (Including 1100 MW from Mangla Dam Raising Project and 969 MW Neelum Jhelum Hydro-Electric Project).
Hydro Power Potential in AJ&K
Sr.# |
Status |
Nos. |
Capacity |
1
|
Commissioned |
22 |
2362.820 |
|
16 |
59.32 |
|
b. WAPDA |
2 |
2069.00 |
|
c.PPC/PPIB |
4 |
234.5 |
|
2 |
Ongoing |
14 |
974.880 |
|
11 |
145.80 |
|
b.PPC/PPIB |
3 |
829.08 |
|
3 |
Upcoming Projects |
59 |
5920.92 |
(24 Feasibility completed Cap: 130.28 MW + 06 PC-I Cap: 77.45 MW) |
30 |
207.73 |
|
b.Project under process in private sector (09 PPIB Cap: 3976.7 MW + 18 AJKPPC Cap: 227.49 MW) |
27 |
4204.190 |
|
c.Raw Sites (Dudhnial: 960 MW, Neelum III & IV 549 MW) |
02 |
1509.00 |
|
|
Total (identified) |
95 |
9258.620 |
Total Estimated Requirements of AJ&K = 400 MW Maximum Power Supply = 330MW
To see/download a Complete picture of Power sector development activities in AJK click on the link below